Strategic Industrial Cluster: Synthetic Graphite Production (CSPG)
Deep Processing Project of National Significance / Republic of Kazakhstan
< 1,5 %
Energy efficiency
175 mvh
Production output
> 70%
Environmental Impact
  • The Role of Graphite
    Often overlooked, graphite is the primary anode material in most commercial lithium-ion battery
Growing applications for CSPG
  • ~18-25%
    Rapid EV adoption globally, policy incentives, automaker investments
  • ~3-5%
    Steady demand for smartphones, laptops, wearables
  • ~20-30%
    Growing renewable integration, grid balancing, demand for large-scale energy storage
  • ~4-8%
    Aerospace, defence, medical devices; increasing application diversity
  • 2025 Global Anode Industry
    China dominates downstream EV battery supply chain, a trend which is unlikely to change
THE CHALLENGE:
Most lack the technology, partners and skills to CSPG quality requirements
HIGH COSTS
EXTENDED QUALIFICATION TIMELINE
NO BINDING OFFTAKES IN PLACE
Fast-Tracking Towards Building Full-Scale CSPG Plant
Construction of an industrial complex for the production of high-purity synthetic graphite (anode material) for electric vehicle batteries and energy storage systems
Summary of the project
Anode plant design in Kazakhstan
Key investment parameters
Indicator
Value
Capacity
247,390 tons/year
The land
60 hectares
Power Consumption
≈ 12-15 MWh/t
Target Market
EV/ESS
Positioning
as an alternative to Chinese imports
Advancing the Value Chain:
From Raw Material to Green Tech
Stage 1
Crude Oil & Kazakhstan Refinery
Petroleum Coke (Low Value Export)
Stage 2
Deep Processing at CSPG
Transformation to Synthetic Graphite
Stage 3
Global Market Application
Anodes for EV Batteries & ESS (High Value Export)
Key Insight:
Currently, petroleum coke is a raw byproduct. This facility introduces a full processing cycle to convert this byproduct into a critical component for the EV industry, achieving true import substitution and significantly increasing domestic value-added production
Technical Specifications & Production Capacity
  • Facility Focus
    Deep processing of petrochemical feedstock
  • Primary Output
    Synthetic graphite, а critical material for the anode side of lithium-ion batteries
  • Production Volume
    Planned capacity of 20,616 tons per month
  • Market Alignment
    Direct application in Electric Vehicles (EVs) and large-scale Energy Storage Systems (ESS)
Energy Independence & Environmental Standards
  • Power Generation:
    Deployment of own gas power generation facilities to ensure energy security and reduce strain оп the regional grid
  • Emissions Control:
    Utilization of modern gas cleaning systems to ensure low СО2 emissions
  • Compliance:
    Full alignment with international ESG (Environmental, Social, and Governance) standards
Geopolitical Positioning:
The Neutral Advantage
  • Reliable Jurisdiction
    Kazakhstan offers а stable, neutral ground for global supply chains
  • Strategic Balance
    The project balances the interests of the EU and Asia in the critical minerals sector
  • Global lntegration
    Enhances national investment attractiveness and secures Kazakhstan's participation in the global EV value chain
Execution Timeline:
24 Months to Launch
Phase 1: Months 0-6
Preparation
FEED (Front-End Engineering Design) & Permitting
Phase 2: Months 6-24
Construction
Facility Construction (18-22 Months)
Phase 3: Month 24
Launch
Commissioning & Full Operations
Rapid deployment capability pending administrative approval